The Antwerp Township Planning Commission is in the process of updating the Parks and Recreation Plan. We ask for your cooperation in completing our online confidential survey, as your participation will help make the Township a better place to live and play. Please find the survey at the following link: https://www.surveymonkey.com/r/antwerprec

Paper copies are also available at the Township Hall.


Mrs. Van is turning 80!  Come out and celebrate on Saturday, November 18 at the Antwerp Township Activity Center (24821 Front Ave) from 11 am – 3 pm with a Birthday Potluck.


 

Indiana Michigan Power (I&M) is upgrading the electric transmission grid in Van Buren and Cass counties in Michigan. The East Valley Upgrades Project is one of two projects in the Valley Area Improvements Program that modernizes the transmission infrastructure to provide a reliable flow of electricity to its customers.

East Valley Upgrades include:
• Rebuilding approximately 17 miles of 69 kilovolt (kV) transmission line
• Upgrading approximately 5 miles of 34.5kV to 69 kV line
• Upgrading approximately 12 miles of single circuit 69 kV to double circuit 69kV/138kV line

East Valley Upgrades – Construction is expected to start in fall 2018 and be completed by spring 2021. Additional information is also available on the project website at www.IndianaMichiganPower.com/ValleyArea